A practical decision table
| Question | Evidence | Owner |
|---|---|---|
| Which part? | Current notice and BOM match | Engineering |
| By when? | Order and shipment dates | Purchasing |
| How much? | Demand, stock and transition assumptions | Operations and finance |
Component continuity
A last-time-buy notice creates a deadline, not an automatic purchase quantity. Confirm which parts are affected, separate ordering from delivery deadlines, and compare a documented inventory bridge with the work needed to approve a replacement.
For purchasing review of supplied notices and quotes. Engineering owns replacement qualification. Our review methodology →
| Question | Evidence | Owner |
|---|---|---|
| Which part? | Current notice and BOM match | Engineering |
| By when? | Order and shipment dates | Purchasing |
| How much? | Demand, stock and transition assumptions | Operations and finance |
A distributor forwards an end-of-life notice for a component used in your access controller. Before asking for a large final order, obtain the manufacturer's notice and match its affected orderable part numbers to your bill of materials. Record the notice identifier, revision and source; a family name alone may not resolve package or grade differences.
Texas Instruments distinguishes not recommended for new designs, last time buy and obsolete. Those labels are not interchangeable. Analog Devices likewise distinguishes lifecycle categories and directs customers to confirm the status of specific models. Use the manufacturer’s current information for the exact part, not an old distributor screenshot.
TI describes separate last-order and final-delivery dates in its discontinuance process. ADI's notice fields likewise include last-time-buy and last-time-ship dates. Read the actual notice and confirm the terms for your purchasing channel; do not turn one supplier's general policy into a universal deadline.
Ask the seller to confirm the final order cutoff, available quantity, delivery schedule and any cancellation or rescheduling restrictions. Record the response date and who provided it. A published deadline does not by itself confirm that your requested quantity has been allocated or your order accepted.
Use this RivetBridge checklist with purchasing, engineering, operations and finance. It is a working review method, not a manufacturer's ordering policy.
A fictional controller team forecasts 1,200 component units for builds and 100 for service through its planned transition. It has 300 usable units in stock and 200 confirmed incoming units. The starting gap is 800 units: 1,200 + 100 − 300 − 200.
That arithmetic is not an approved order. It excludes any additional allowance for losses or forecast uncertainty, and assumes the incoming stock arrives in time. If the replacement schedule slips, demand may change. Keep those assumptions visible rather than quietly adding an unexplained buffer.
A suggested alternative is a candidate for engineering review, not permission to substitute it on a production order. Ask the responsible team to assess the relevant electrical, mechanical, firmware and qualification differences. Preserve the approved baseline until the change is accepted.
Finish with one decision: place a scoped bridge order, obtain missing evidence, pursue a replacement review, or reconsider the product-support plan. Record the owner and next review date. Procurement can organize the evidence, but cannot promise lifetime availability or eliminate inventory risk.
APPLY THIS TO YOUR COMPONENT